Installation method

Video for Installation method

Installation procedures

  •  

    1Preparation for installation

    • Plan the best layout for the floor heating pipe
    • Clean the floor
    • Lay the insulation sheets if required
  •  

    2Install the bottom panels of HOYA ONDOL

    • Start laying the panels. Lay panels side by side along the edge of a wall in the most appropriate orientation.
    • Continue to lay panels across the rest of the floor.

    ※ Note: Take care to align panels accurately.

  •  

    3Install the Pex(PE-RT) pipe

    • The size of the pipe is 12mm(ID) and 16mm(OD).
    • Roll out the pipe pushing it into the channels of the bottom panels
    • Unroll the pipe hand over hand to avoid twisting
    • Do not kink the pipe by trying to make a very tight turn.
    • The pipe should run start and finish at the manifold, by fitting the manifold in place before laying the pipe. Allow sufficient pipe for cutting and fitting at a later stage
  •  

    4Install the top panels of HOYA ONDOL

    • Snap-fit the top and bottom panels
    • Use the rubber mallet hammer for easy work
  •  

    5Connect the pipes to the manifold

    • Connect the pipes to the manifold by using coupling sockets
    • Be careful not to kink the pipes
  •  

    6Connect the boiler

    • Connect the manifold to the boiler by certified engineer according to the local regulation.
  •  

    7Completion of installation

    • Commissioning
  •  

    8Install the flooring material

HOYA ONDOL is the unique hydronic radiant system for easy installation and energy saving.